A quick tour of https://casinoniccasinos.com instantly provides an overview of the many possibilities on offer. Navigation is clearly structured and allows the desired content to be found quickly. Telephone support offers an alternative contact channel for more complex inquiries. Side bets expand the strategic options at classic tables. New players are welcomed with a comprehensive welcome package spread across several deposits. Crypto withdrawals are usually confirmed within 10 to 30 minutes. Themed slots with mythological, adventure or fantasy backgrounds create an immersive atmosphere. A cookie banner informs transparently about the use of tracking technology. Special missions during holidays lend the regular game routine an additional flavour. Push notifications inform players about new promotions and personal bonus offers. In comparison with established competitors, the casino proves consistently competitive.
6090-EPC-MPQ & DSO HarbourLiberia
● PMC / AMC: DMRC
● Main Contractor: Afcons Infrastructure Ltd.
● Scope of Work: Offshore activities including underwater seabed surveys, marine craft support and rescue operations
Khandwa Intake Well Charkheda Pump House, Madhya Pradesh
● PMC / AMC: Mehta Consultant
● Main Contractor: CMR Infrastructure Pvt. Ltd.
● Scope of Work: Underwater core cutting in intake well: 3 nos., approx. 1000 mm dia (or square) in 500 mm thick concrete wall
EPCI of Second Liquid Cargo Berth at GCPL, Dahej, Gujarat.
● PMC / AMC: RPMG
● Main Contractor: Afcons Infrastructure Ltd.
● Scope of Work:Carry out all underwater works instructed by the contractor for the project
Mumbai Coastal Road Project PKG-2 Worli, Mumbai
● Consultant: AECOM
● Main Contractor: HCC – HDC JV
● Subcontractor: International Divers Aquarium
● Scope: Underwater mooring pile cutting (1m, 2m & 3m dia)
● Duration: Jan 2024 – Feb 2025
● Outcome: Work completed successfully
IOCL Captive Jetty Project Kamarajar Port Ltd. Chennai
● Consultant: TEPL
● Main Contractor: ITD Cementation India Ltd
● Scope: Underwater diamond wire saw cutting of RCC piles for IOCL captive POL/LPG marine jetty & associated facilities
● Duration: Oct 2023 – Jul 2025
● Outcome: Work completed successfully
Underwater Diaphragm Wall Repair at Berth 3, Kakinada SeaPort
● Consultant: L&T Infrastructure Engineering Ltd
● Main Contractor: International Divers Aquarium
● Scope: Underwater repair of concrete diaphragm wall between Bollards 23 & 24 at Berth 3, Kakinada Port
● Duration: Oct 2020 – Mar 2021
● Outcome: Work quality found satisfactory
Greater Male’ Connectivity – Male’ to Thilafushi Link Project, Maldives
● Consultant: Arup Ltd
● Contractor: Afcons Infra Ltd
● Scope: Silt screen, geotextile & rock works
● Duration: Jun–Dec 2022
● Outcome: Completed successfully
100 MLD SWRO Desalination plant, Dahej, Gujarat
● Contractor: L&T–Tecton JV
● Scope: Underwater liner cutting & concrete breaking
● Duration: Feb–Apr 2022
● Outcome: Work completed satisfactorily
Nouakchott Container Terminal on EPC basis at Nouakchott
● Consultant: EGIS Intl
● Contractor: Afcons Infra Ltd, Mauritania
● Scope: Supply of divers for Nouakchott Terminal
● Duration: Dec 2019 – Oct 2020
● Outcome: Completed successfully
Underwater Beam Repairing and Groove Maintenance
● Contractor: Civil Index Construction Pvt. Ltd
● Scope: Underwater beam repair & groove maintenance
● Duration: Oct 2019 – Jan 2020
● Outcome: Completed successfully
Hydro Power Plant
Maintenance
● Contractor: Gill Acqua Hydro Power Generation Co. Pvt. Ltd
● Scope: Underwater videography, photography, inspection & gate sealing
● Duration: Feb–Mar 2019
● Outcome: Work completed satisfactorily
Construction Of Greenfield Port at Ramayapatnam on Engineering
● Consultant: NECL–ARIPL JV
● Contractor: Auro Infra Pvt. Ltd
● Subcontractor: International Divers Aquarium
● Scope: X-Bloc placing & underwater videography
● Duration: Oct 2023 – Oct 2024
● Outcome: Completed successfully
Corrosion Protection to Quay Structures at Port Louis Harbour
● Contractor: Del Seatek India Pvt. Ltd
● Scope: Supply & installation of aluminum anodes with brackets, marine growth removal, and surface prep at Quays 1–4, A, D, E, Trou Fanfaron & Port Mathurin
● Duration: Sep 2018 – Mar 2019
● Outcome: Work completed successfully
Channel Cutting work for NTPC LTD, Super Thermal Power Rihandnagar
● Contractor: Paharpur Cooling Towers Ltd
● Scope: Diamond wire cutting of channel wall for modification & installation of cooling towers
● Duration: March 2019 Executed within schedule with strict adherence to safety and quality standards.
● Outcome: Work completed successfully
Kudankulam Nuclear Power Project Units – 3&4 Tirunelveli, Tamilnadu
● Consultant: AECOM
● Contractor: Sanjay Construction Company
● Scope: Underwater block placing, drilling & blasting works
● Duration: Dec 2018 – Oct 2019
● Outcome: Work completed successfully
Construction of Coal Berth no 3 & 4 KPL
● Consultant: Howe (India) Pvt. Ltd
● Contractor: Afcons Infrastructure Ltd
● Scope: Dry & underwater diaphragm wall repair (450m × 25m) and geotextile layer
placement for slope protection
● Duration: Feb 2017 – Dec 2018
● Outcome: Work completed successfully
Construction of Oil jetty Project Liberia
● Consultant: Royal Haskoning DHV
● Contractor: Afcons Infrastructure Ltd
● Scope: Underwater survey, sheet pile cutting (100m), welding (150m), steel fit-ups (10 MT) & sheet pile installation (50 MT)
● Duration: Jan – Jun 2013
● Outcome: Work completed successfully